Change Order: Approval Process, Pricing, Typical Volume, Triggers, Schedule Impact, Required Contents, Types, Legal Status, Code and Permit Limits, Payment Terms

An interior designer and homeowner review a floor plan on a tablet to finalize a change order for their kitchen remodel on a page about Change Order: Pricing, Approval Process, Triggers, Typical Volume, Required Contents, Schedule Impact, Legal Status, Types, Payment Terms, Code and Permit Limits

A change order is a written document that modifies the agreed scope, price, or schedule of an existing remodeling contract. Key aspects include pricing, approval process, triggers, typical volume, required contents, schedule impact, legal status, types, payment terms, and code and permit limits. On a remodeling project, it records any adjustment made after the original contract is signed, so both parties share the same updated terms. Changes usually arise from hidden conditions, owner requests, material substitutions, or code requirements, and each one affects cost and timing. Every remodeling company relies on this paperwork to keep the project’s budget and schedule accurate as work progresses. This article explains what triggers these changes, how they are priced, how often they typically occur, what each document must contain, and how approval works before the new work begins.

Key Takeaways

  • A change order modifies the original contract scope of work, price, or schedule.
  • Total change orders usually range from 5% to 10% of the original contract value.
  • Keep a 10% to 20% contingency reserve to cover unexpected costs during your remodel.
  • Overhead and profit markup typically adds 10% to 20% to the direct project costs.
  • Complete documents require 2 signatures before you authorize work to start.

What Causes a Change Order During a Home Remodel?

A change order is typically triggered by events that deviate from the initial plans or expectations established when you signed the original contract. These modifications often stem from physical realities discovered once construction begins, intentional adjustments you choose to make to the design, or external requirements that compel an alteration to the work.

Change Order DriverPrimary Risk FactorBudget Impact Estimate
Unforeseen ConditionsStructural decay, hazardous materials, or latent site issuesHigh (Requires immediate reserve)
Owner-Requested UpgradesChanges in aesthetic finishes or functional scopeModerate to High (Discretionary)
Code and Inspection MandatesRegulatory compliance for safety and structural standardsMandatory (Non-negotiable)
Material UnavailabilitySupply chain disruptions or product discontinuationsLow to Moderate (Logistical)
Design Errors or OmissionsMeasurement inaccuracies or engineering oversightsModerate (Correction based)

Recommended Contingency Reserve Range

Minimum Reserve
10%
Maximum Reserve
20%
  • Unforeseen conditions: Discovering structural rot, mold, outdated wiring, or asbestos behind walls or under floors during demolition.
  • Homeowner-requested upgrades: Deciding to switch to higher-end tile, adding extra electrical outlets, or choosing different cabinetry after work has started. Per the American Institute of Architects, discrepancies between initial design specifications and owner-requested material upgrades frequently necessitate formal adjustments to the original building contract.
  • Code and inspection requirements: Mandatory modifications issued by local authorities to bring systems up to current safety or structural codes.
  • Material unavailability: Necessary substitutions when chosen materials are discontinued or stuck in long-term supply chain delays.
  • Design errors or omissions: Corrections required because the original plan failed to account for site-specific measurements or engineering constraints.

Before beginning your project, walk through the space with your contractor to identify potential problem areas so you can establish a contingency reserve of 10% to 20% to cover the costs of these likely adjustments.

To effectively manage change orders during your project, consider these proactive strategies:
  • Verify that all verbal agreements regarding design changes are formalized in a written change order document before work proceeds.
  • Request a detailed breakdown of costs from your contractor, separating labor expenses from material price fluctuations.
  • Ensure your contract includes a defined process for change order approvals to prevent unauthorized work or unexpected billing.
  • Conduct a final walkthrough before the project concludes to reconcile all pending change order adjustments against the initial contract scope.
This summary card explains how a change order updates project scope and budget expectations during a home renovation.

How Is the Price of a Change Order Calculated, and What Markup Is Normal?

You calculate the price of a change order by taking the direct costs of the adjusted scope of work and adding an overhead and profit markup of roughly 10% to 20%, noting that typical change orders generally amount to 5% to 10% of the original contract value. Per the National Association of Home Builders, the total price for a change order typically includes the direct cost of labor and materials plus a contractor markup to cover overhead and profit.

Cost CategoryDescription of InclusionsTypical Allocation
Direct CostsLabor, materials, specialized subcontractor invoices, and equipment rentals5% – 10% of total contract value
Overhead & ProfitAdministrative fees, business operating expenses, and contractor net earnings10% – 20% markup on direct costs

Typical Change Order Components (Percentage of Original Contract)

Direct Costs
5% – 10%
Overhead & Profit
10% – 20%

What Goes Into the Direct Cost of a Change Order

The price of a change order is calculated by aggregating the specific labor, material, and subcontractor expenses necessary to perform the adjusted work. This direct cost represents the actual amount the contractor must spend to execute the physical modification. When building your budget for these shifts, distinguish between hard expenses and the administrative fees added later.

  • Direct Labor: Hourly or fixed rates for the personnel executing the new tasks.
  • Materials: The specific items, components, or finishing products required for the change.
  • Subcontractor Charges: Invoices from specialized trades, such as electricians or plumbers, brought in for the adjustment.
  • Equipment Rental: Costs for specialized tools or machinery needed solely for the added scope.

What Overhead and Profit Markup Is Normal?

The combined overhead and profit markup added on top of direct costs is roughly 10% to 20%. This percentage covers the contractor’s administrative time, insurance, and the margin required to maintain business operations while managing the redirection of project resources.

How Markup Applies to Deductive Change Orders

In a deductive change order, which removes work from the original contract, the contractor may still apply a partial markup adjustment. While you receive a credit for the avoided direct costs, the contractor often retains a portion of the original overhead to offset the administrative effort of managing the cancellation or logistical shift.

How a Change Order Affects the Revised Contract Total

A change order impacts the revised contract total by adding or subtracting the net cost of the modification from the original balance. Because this document functions as a legal addendum, the final figure serves as the new benchmark for payment schedules and future progress installments. Confirm that the document explicitly states whether the cost adjustment includes all taxes and delivery fees before you apply your signature.

Consider these additional factors when refining your change order estimates to ensure comprehensive coverage:
  • Permit Fees: Costs associated with filing updated plans or obtaining municipal approvals for the revised scope.
  • Design and Engineering: Fees for architectural revisions or structural consultations required by the modification.
  • Site Protection: Expenses for extra cleaning, waste removal, or temporary barriers necessitated by the specific change.
  • Schedule Impact: Costs related to potential project delays, such as extended site supervision or additional equipment rental durations.

How Much Change Orders Usually Add to a Budget and How Big Your Contingency Reserve Should Be

Change orders usually add 5% to 10% of the original contract value to your total project budget, while a prudent contingency reserve should be set between 10% to 20% of the overall project budget to accommodate these adjustments. Per the National Association of Home Builders, it is a standard industry recommendation to maintain a contingency budget of at least 10% to 20% of the total project cost to account for both elective change orders and unforeseen site conditions. Because remodeling often involves older structures where unforeseen conditions remain hidden behind walls or beneath flooring, maintaining a dedicated financial cushion is essential to avoid project stalls when a necessary change order arises. Without this buffer, you may find your renovation halted if you cannot immediately fund the additional labor, material, or permit costs required to bring the work up to standard.

Change Order CategoryFinancial ImplicationOperational Consequence
AdditiveIncreases total contract expenditureFunds new requests or structural remediation
DeductiveDecreases total contract expenditureRemoves scope or utilizes lower-cost materials
No-Cost / Time-OnlyNeutral on direct project budgetExtends completion timeline; increases secondary living costs

Estimated Budget Impact Percentages

Change Order Impact
5% – 10%
Contingency Reserve
10% – 20%

Planning for these costs requires an understanding of how different types of changes impact your financial planning:

  • Additive change order: Increases your total expenditure to cover new requests or to rectify uncovered structural issues.
  • Deductive change order: Reduces your total expenditure if you decide to remove a specific item or switch to a less expensive material.
  • No-cost or time-only change order: Maintains your current budget but may shift your expected completion date, which could indirectly impact costs like temporary housing or storage fees.

Review your financial standing by evaluating whether your liquid assets can cover the high end of your contingency reserve without relying on credit lines that could jeopardize the project if interest rates or borrowing terms fluctuate.

To ensure your renovation remains financially resilient, consider these strategic approaches to managing project scope and expenses:
  • Document every change request in writing via a formal change order form to prevent scope creep and ensure clear communication.
  • Prioritize “must-have” structural repairs over aesthetic upgrades when utilizing your contingency reserve.
  • Establish a payment schedule that requires approval of all cost adjustments before the relevant phase of work begins.
  • Review the original contract’s clause regarding “unforeseen conditions” to understand how your contractor handles unexpected issues behind walls or flooring.

What a Change Order Should Include to Be Complete

A change order includes specific legal and financial details to be complete, ensuring that the alteration to the original contract remains enforceable and clearly documented for both parties. Per the Federal Trade Commission, it is essential that these documents provide a clear, written description of modifications to the project scope alongside the corresponding adjustments to the total contract price. Without these comprehensive data points, the amendment leaves the project vulnerable to disputes regarding expectations, payments, or the timeline.

Change Order ComponentRequired Data AttributeLegal & Financial Purpose
Scope DefinitionDetailed NarrativePrevents disputes regarding physical modifications
Change RationaleJustificationProvides evidence for unforeseen conditions or owner requests
Cost ImpactLabor, Material, Overhead & ProfitEnsures transparent pricing for the contract adjustment
Timeline ModificationNet Calendar/Working DaysUpdates project completion expectations
Contractual TotalCumulative Price SumEstablishes the final, enforceable financial obligation
ExecutionDual Signatures & DateFormalizes the legal amendment of the agreement
  • Detailed Scope of Work: A precise narrative describing the physical additions, removals, or material swaps involved.
  • Justification: The reason for the change, such as the discovery of unforeseen conditions or an owner-requested upgrade.
  • Financial Adjustment: The explicit net impact on the price, including the specific cost of labor, materials, and the applied overhead and profit markup.
  • Schedule Impact: The exact number of calendar or working days added to or removed from the projected completion date.
  • Revised Contract Total: The new, updated final price of the project after accounting for the change.
  • Formal Execution: The date and exactly 2 required signatures, one from the homeowner and one from the contractor.

Review the document to confirm that the revised contract total reflects the sum of the original price and all previous change orders before you provide your signature.

To ensure administrative compliance and project alignment, consider these additional practical requirements for your change order documentation:
  • Attachment Inclusion: Append site photographs, updated architectural drawings, or technical specifications to visualize the proposed changes.
  • Payment Terms: Specify whether the adjustment is due upon completion of the change, added to the next progress billing, or subject to a deposit.
  • Subcontractor Impact: Note any effects the modification has on trade partner schedules or long-lead material procurement.
  • Permit Updates: Include a reference to whether the modification necessitates revised building permits or municipal inspections.
  • Waiver Clause: Include language stating that the change order acts as a waiver of any future claims related to the specific work described within this amendment.

The Step-by-Step Process for Approving a Change Order, and Whether Work Can Start Before You Sign

The step-by-step process for approving a change order consists of five specific phases to ensure accountability, and work should never start before you sign the document unless a critical emergency necessitates immediate action. Following a structured procedure protects the integrity of your original contract and prevents disputes regarding the scope of work or the revised contract total. Per the American Institute of Architects, standard industry practice dictates that a change order should clearly define the change in work, the adjustment to the contract sum, and the modification to the project schedule before the work is authorized to begin.

PhaseKey ResponsibilityPrimary Risk Mitigation
IdentifyDocumenting the trigger (unforeseen condition, upgrade, or design shift)Prevents unauthorized scope creep
PriceQuantifying labor, materials, overhead, and schedule delaysEnsures budget transparency
ReviewValidating alignment between proposed work and owner expectationsEliminates post-project scope disputes
SignExecuting the legal addendum with dual-party authorizationRemoves reliance on unenforceable verbal agreements
ProceedCommencing work only upon full document executionProtects against liability and unauthorized costs
  1. Identify: You or the contractor recognize a need for a change based on a discovery of unforeseen conditions, a requested upgrade, or a design adjustment.
  2. Price: The contractor calculates the cost and schedule impact, applying the necessary overhead and profit markup to the direct expenses.
  3. Review: You examine the proposed change order to ensure the description of work and the adjusted completion date align with your expectations.
  4. Sign: Both you and the contractor must provide your 2 signatures to authorize the document as a legal addendum to the original contract.
  5. Proceed: The contractor begins the new work only after the fully executed document is in hand.

Verbal agreements regarding modifications are frequently unenforceable and create significant risk for both parties, so you should insist that every change order is finalized in writing before any labor or material purchases occur. Verify that the documented schedule impact accounts for all secondary delays, such as time required for re-permitting or shipping special-order components.

Follow these operational best practices to maintain a smooth change order workflow:
  1. Distribute copies of the fully executed change order to the project superintendent and accounting department immediately to ensure field execution and billing accuracy.
  2. Update the master project schedule to reflect any time extensions formally granted within the agreement.
  3. Maintain a centralized change order log to track the status, approval dates, and cumulative impact on the contingency budget.
  4. Archive all supporting documentation, such as site photos or original submittal requests, alongside the signed contract addendum for future audit purposes.

Frequently Asked Questions

What are the different types of change orders in a remodeling project?

There are 3 main forms of change order used in remodeling: an additive change order for additional work and costs, a deductive change order for removing work to receive a credit, and a no-cost or time-only change order for swapping materials or adjusting the schedule without changing the original contract price.

How does a change order affect my remodeling completion date?

A change order affects your remodeling completion date by adjusting the timeline in calendar or working days, ranging from no change for simple material swaps to several weeks for re-permitting or special-order items. You and the contractor must explicitly state the revised finish date within the signed document.

Is a change order legally binding, and can a contractor charge extra without a signed one?

Yes, a change order is a legally binding addendum to your original contract once signed by both the homeowner and contractor. You should avoid verbal agreements because they are often unenforceable, and many states require these modifications to be in writing to protect both parties from future payment disputes.

When do I have to pay for a change order: upfront, with the next progress payment, or at the end?

Payment terms for a change order are determined by your specific agreement with the contractor, who may request the amount upfront, include it in your next progress payment, or add it to the final invoice. Always clarify these terms before signing the document to ensure your payment expectations align.

Do change orders involving electrical, plumbing, or structural work need new permits or inspections?

Yes, change orders involving significant mechanical or structural modifications often require new permits or inspections as part of the legal process. These code requirements are common triggers for a change order, and you must include the associated time and costs for these municipal approvals within the finalized document.